风管系统安装后不按规定作漏光、漏风检查和试验 |
添加时间:2023/9/19 16:31:13 浏览次数: |
风管安装前应清除内、外杂物,并做好清洁和成品,施工后及时封堵管口,如不清除杂物,将会造成系统阻力增大,严重时堵塞过滤网和管道。 Before the installation of the air duct, the internal and external sundries shall be removed, and the cleaning and finished products shall be well prepared. After the construction, the pipe orifice shall be blocked in time. If the sundries are not removed, the system resistance will increase and the filter screen and pipeline will be blocked in serious cases. 2、风管系统安装后不按规定作漏光、漏风检查和试验 2. After the installation of the air duct system, the light and air leakage inspection and test are not conducted according to the regulations 漏光或漏风量测定是对通风空调施工质量的一项检验措施,必须严格按要求规范进行检验,若风管系统安装后不按规定作漏光、漏风型线 流水槽模具 景观石 检查井钢模具 保定通风管道 重庆窗帘 隔离墩模具 保定保洁公司检查和试验,可能会造成系统大量漏风,使整个系统和项目工程达不到使用要求,增加不必要的返工和浪费,同时也浪费了能源。 The measurement of light leakage or air leakage is an inspection measure for the construction quality of ventilation and air conditioning, which must be inspected in strict accordance with the requirements and specifications. If the air duct system is not inspected and tested according to the regulations after installation, it may cause a large amount of air leakage in the system, make the whole system and project project fail to meet the use requirements, increase unnecessary rework and waste, and waste energy at the same tim |
上一页 漏光或漏风量测定是对通风空调施工质量的一项检验措施 |
下一页 螺旋风管的用途是什么? |
Copyright © 技术支持:遨游网络